Location: London
Value: £140,000
Programme: 42 Weeks
The project included the demolition of the existing pavilion and small buildings and the construction of a new pavilion in its place.
The scope of works called for the design, co-ordination, supply, installation, test and commissioning of a complete and fully functional electric and data system.
Working closely with the design team, the look was to be minimalistic, with only specialist timber internal walls and ceilings on show where possible.
Ground floor included washrooms, toilets, changing rooms, a medical room and office.
On the top floor, a club house and kitchen were installed for guests.
Electrical Installation:
Delivery of new utility services to the site
Lighting, emergency lighting and feature lighting including the external LED street lighting
Complete small power and distribution installation
Kitchen and preparation room
Fire alarm
CCTV and security
Data installation
TV network installation
Disabled alarm
Lighting protection
Test and commissioning of services